Xinjiang: wind abandonment rate from January to February was 17.6%, with a year-on-year decrease of 1.7 percentage points
Time: 2019/3/29 13:47:58

Polaris wind power grid    Source: Polaris wind power grid      2019/3/29 9:04:38   


Recently, the亿电竞 development and Reform Commission of Xinjiang Uygur Autonomous Region released wind power operation data from January to February. The亿电竞平台 following is the亿电竞 original text:


Xinjiang: wind power abandonment rate continued to decline from January to February

In February 2019, the亿电竞 wind power operation in the亿电竞 autonomous region continued to improve, and the亿电竞 utilization hours of equipment decreased slightly year on year, Abandon the亿电竞 wind The亿电竞平台 situation of power rationing had a steady decline year on year.


1、 Wind power operation

(1) installed capacity: by the亿电竞 end of February 2019, the亿电竞 installed power generation capacity of Xinjiang power grid is 86.595 million kilowatts. Among the亿电竞m, the亿电竞 installed capacity of wind power is 19.251 million kilowatts, accounting for 22.2% of the亿电竞 total installed capacity.

(2) equipment utilization: in February 2019, the亿电竞 average utilization hours of all power generation equipment in Xinjiang power grid dispatching caliber are 267 hours, an increase of 17 hours over the亿电竞 same period of last year. Among the亿电竞m, the亿电竞 average utilization hours of wind power equipment was 106 hours, a decrease of 39 hours compared with the亿电竞 same period of last year.

From January to February of 2019, the亿电竞 average utilization hours of power generation equipment in Xinjiang power grid dispatching caliber (networking operation) was 569 hours, an increase of 37 hours on a year-on-year basis, including 240 hours of wind power, with a year-on-year decrease of 17 hours.


2、 Wind power production

In February 2018, the亿电竞 total power generation of Xinjiang power grid dispatching caliber was 23.1 billion kwh, with a year-on-year increase of 8.2%. Among the亿电竞m, wind power was 2.54 billion kwh, an increase of 26.8% year-on-year, accounting for 10.9% of the亿电竞 total power generation.

From January to February 2019, the亿电竞 total power generation of Xinjiang power grid dispatching caliber is 49.2 billion kwh, with a year-on-year increase of 8.2%. Among the亿电竞m, wind power was 4.43 billion kwh, a year-on-year decrease of 3%, accounting for 9% of the亿电竞 total power generation.


3、 The亿电竞平台 current situation of wind abandonment in the亿电竞 Autonomous Region

In February 2019, the亿电竞 wind power curtailment in our region is 590 million kwh, an increase of 3.5% over the亿电竞 same period last year; the亿电竞 wind abandonment rate is 18.9%, a year-on-year decrease of 3.9%. From the亿电竞 regional perspective, the亿电竞 wind power consumption in Bozhou and Bazhou is relatively good, with wind power abandonment rates of 13.3% and 5.9% respectively; the亿电竞 wind power consumption situation in Changji Prefecture is not optimistic, and the亿电竞 wind power abandonment rate is far higher than the亿电竞 average level of the亿电竞 whole region, reaching 30.2%.

From January to February in 2019, the亿电竞 wind power curtailment in our region is 950 million kwh, a year-on-year decrease of 12.8%, The亿电竞平台 wind abandonment rate was 17.6%, a year-on-year decrease of 1.7 percentage points.

Next, the亿电竞 development and Reform Commission of the亿电竞 autonomous region will continue to strengthe亿电竞n the亿电竞 supervision of wind power consumption and optimize the亿电竞 consumption environment. Strictly implement the亿电竞 national laws and regulations and relevant policies, strengthe亿电竞n the亿电竞 supervision and management of renewable energy consumption in the亿电竞 whole region, and create a good market environment for the亿电竞 production and operation of new energy in the亿电竞 whole region.

 